![]() [PRODUCTS PAGE, HOME] |
|
| Catalog provided courtesy of The Crosby Group, Inc. | |
| Crosby Swiveling Overhaul Ball Inspection Report - Form #8 |
| CROSBY SWIVELING
OVERHAUL BALL INSPECTION
|
FREQUENT VISUAL
INSPECTION BEFORE EACH SHIFT AND PERIODIC INSPECTION AT LEAST ANNUALLY
(QUARTERLY AND MONTHLY IN HEAVY OR SEVERE USE) |
BY: DATE: SITE: SIZE: |
|||||||
| OVERHAUL BALL LOCATION, EQUIPMENT, OR I.D. |
BASIC INSPECTION SEE CODE BELOW |
LINK PLATES |
BOLTS,
NUTS, SLEEVES |
BALL | HOOK | SWIVEL | OTHER POINTS DETERMINED BY USER BASED ON APPLICATION |
![]() |
|
| BASIC INSPECTION CODE AA CRACKING OR IMPACT DAMAGE AB MODIFICATION SUCH AS WELDING OR CUTTING AC SUBSTITUTION OF PARTS AD RESTRICTED MOVEMENT OF SWIVEL AE EXCESSIVE WEAR AG EXCESSIVE DEFORMATION FOR OVERHAUL BALL CAPACITIES LESS THAN 12 TONS THERE ARE NO MACHINED SURFACES. THE SWIVEL TO END FITTING CLEARANCES SHOULD BE CHECKED AND IF FOUND TO EXCEED .180", THE SWIVEL SHOULD BE REMOVED FROM SERVICE. REPLACE SWIVEL DO NOT DISASSEMBLE. FOR OVERHAUL BALL CAPACITIES 12 TONS AND LARGER THERE ARE MACHINED SURFACES. THE SWIVEL TO END FITTING CLEARANCES SHOULD BE CHECKED AND IF FOUND TO EXCEED .125" TO .180", THE SWIVEL SHOULD BE REMOVED FROM SERVICE. |
BASIC LUBRICATION
REQUIREMENTS PRESSURE LUBRICATION FITTINGS ARE PROVIDED ON ALL SIZES. USE A LITHIUM BASED GREASE OF MEDIUM CONSISTENCY. THE FREQUENCY OF LUBRICATION DEPENDS ON FREQUENCY AND PERIODS OF USE, ENVIRONMENTAL CONDITIONS, AND THE USER'S GOOD JUDGMENT. AS A MINIMUM LUBRICATION SCHEDULE SHOULD INCLUDE: EVERY 14 DAYS FOR FREQUENT SWIVELING EVERY 45 DAYS FOR INFREQUENT SWIVELING EXCESSIVE WEAR IS CAUSE FOR REMOVAL FROM SERVICE, DO NOT ALLOW MORE THAN: 5% WEAR IN CRITICAL AREA OF HOOK 10% WEAR IN OTHER AREAS OF HOOK 10% WEAR IN OTHER DIMENSIONS, INCLUDING JAW AND EYE |
(Sample Inspection Form #8) The user must edit as needed.
| Copyright © 2000 The Crosby Group, Inc. All rights reserved. |